Description
The project involved the amalgamation of three existing commercial units into one unit and changed its use to Cavan Civil Defence Headquarters, incorporating vehicle/equipment storage, training facilities, canteen/welfare facilities and office space and all other associated works. Demolition of the 3 individual internal office areas in each unit was carried out. Demolition of existing ground floor slab was done to allow for pad foundations for new steel frame to be constructed. Installation of new internal two storey office/administration space was completed. Installation of all associated site works including standard power supply, data supply, foul sewer connections, surface water sewer connections and connection to existing watermain and all other associated services related works including floor finishes, ceiling finishes painting, electrical work, etc., was completed.